A win-win relationship: Climate protection programme and storage systems
In December 2019, EDF Renewables and malt-producer Malteurop commissioned two battery storage systems in Rostock and Heidenau. Each battery is designed to supply the respective production plant with 200 kW for at least one hour.
For malt-producer Malteurop, in addition to cost savings, an equally strong motivation was that storage solutions help stabilize the entire grid and thus ensure reliable power supply for all consumers.
Services by EDF Renewables Deutschland
- Analysis of load and location including battery sizing
- Financing: Coverage of all investments
- Coverage of necessary application procedures (building permit and grid connection)
- Installation: Battery procurement, connection and commissioning
- Regular preventive maintenance and battery control
Technical details
- 200 kW power
- 240 kWh capacity
- Lithium iron phosphate (LiFePO4/LFP)
- 108 modules, 3 racks
- 20-foot container
- Connection to the medium-voltage grid
- Potential cost savings per year: more than 45.000 Euro